Maplewood Township today announced a number of milling and paving projects to take place DATES: Thursday December 13, 2018, Friday December 14, 2018, Monday December 17, 2018 and Tuesday December 18, 2018:

1. JEFFERSON AVENUE:

Phase 1 (Ridgewood Road to Maplewood Avenue) Thursday December 13, 2018 – Milling

Phase 2 (Maplewood Avenue to Valley Street) Thursday December 13, 2018 – Milling

Milling and resetting manholes will start/finish on Thursday December 13, 2018. Paving, striping and signage will start/finish on Friday December 14, 2018.

2. COURTER AVENUE:

Phase 1 (Prospect Street to Oakland Road) Friday December 14, 2018 – Milling

Phase 2 (Prospect Street to Oakland Road) Monday December 17, 2018 – Paving

Milling and resetting manholes will start/finish on Friday December 14, 2018. Paving, striping and signage will start/finish on Monday December 17, 2018.

3. SCHAEFER ROAD:

Phase 1 (Newark Way to Porter Road) Monday December 17, 2018 – Milling

Phase 2 (Newark Way to Porter Road) Tuesday December 18, 2018 – Paving

Milling and resetting manholes will start/finish on Monday, December 17, 2018. Paving, striping and signage will start/finish with paving Tuesday December 18, 2018.

4. FRANKLIN AVENUE:

Phase 1 (Princeton Street to Prospect Street) Monday December 17, 2018 – Milling

Phase 2 (Princeton Street to Prospect Street) Tuesday December 18, 2018 – Paving

Milling and resetting manholes will start/finish on Monday December 17, 2018. Paving, striping and signage will start/finish on Tuesday December 18, 2018