Driver Alert: North Wyoming Ave. Construction in South Orange

by
0 FacebookTwitterPinterestEmail

From the South Orange Police Dept.:

ROAD CONSTRUCTION TRAFFIC NOTICE:

Starting on Wednesday August 5th, (weather permitting), Essex County will begin milling and paving North Wyoming Avenue from the West Orange line (Luddington Rd) to West South Orange Ave. Milling should take three days and will start on 8/5. Paving will commence the following week, date to be announced. Construction will be broken up into three sections (indicated below). Sections not being worked on will remain drivable but may have some traffic interruption(s). Parking restrictions on Wyoming Ave to take effect on 8/5. Please plan your commute accordingly and as always, share this notice to help get the word out.

Schedule:
Wednesday – Luddington Rd to Forest Rd
Thursday – Forest Rd to Tillou Rd
Friday – Tillou Rd to West South Orange Ave

North Wyoming Paving