PSE&G Paving in Maplewood Starts Monday, April 24

by
0 FacebookTwitterPinterestEmail

From Maplewood Township:

 PSE&G will begin paving on Monday on the below schedule. Dates may be changed due to weather.

 

Street Between Street 1 Between Street 2

Milling Date

Paving Date

Lenox Pl Ridgewood Rd Maplewood Ave

24-Apr

27-Apr

Maplewood Ave Baker St Mountain Ave

24-Apr

27-Apr

Winthrop Pl Ridgewood Rd Maplewood Ave

25-Apr

27-Apr

Mountain Ave Ridgewood Rd Maplewood Ave

25-Apr

28-Apr

Carlton Ct Ridgewood Rd Cottage Ct

25-Apr

28-Apr

Cottage Ct Ridgewood Rd Carlton Ct

25-Apr

28-Apr

Berkley Rd Ridgewood Rd 470′ E of Myrtle

26-Apr

28-Apr

Ridgewood Rd Bailey Rd Lenox Pl

26-Apr

28-Apr

Ridgewood Rd Lenox Pl Durand Rd

27-Apr

1-May

 

Updated paving letter-6300