From Maplewood Township:
PSE&G will begin paving on Monday on the below schedule. Dates may be changed due to weather.
| Street | Between Street 1 | Between Street 2 |
Milling Date |
Paving Date |
| Lenox Pl | Ridgewood Rd | Maplewood Ave |
24-Apr |
27-Apr |
| Maplewood Ave | Baker St | Mountain Ave |
24-Apr |
27-Apr |
| Winthrop Pl | Ridgewood Rd | Maplewood Ave |
25-Apr |
27-Apr |
| Mountain Ave | Ridgewood Rd | Maplewood Ave |
25-Apr |
28-Apr |
| Carlton Ct | Ridgewood Rd | Cottage Ct |
25-Apr |
28-Apr |
| Cottage Ct | Ridgewood Rd | Carlton Ct |
25-Apr |
28-Apr |
| Berkley Rd | Ridgewood Rd | 470′ E of Myrtle |
26-Apr |
28-Apr |
| Ridgewood Rd | Bailey Rd | Lenox Pl |
26-Apr |
28-Apr |
| Ridgewood Rd | Lenox Pl | Durand Rd |
27-Apr |
1-May |